The Barn Project

Above is a picture of the Club yard taken in April 2010. As you can readily see we have a Barn. The Barn is in slightly less than perfect condition but that's all about to change...

This years project is to rebuild and extend the barn into a modern and usable building for the club.

In early February 2012 Bob held a number of meetings to outline and kick start the rebuild.

Please revisit this page often, I will try to provide updates and photographs of the project as it progresses.

The start of the project

100_6435web

Here is the Barn at the start of October 2014. It really is the same building. The doors are about to be fitted and one wall still needs some work. We are keen to finish this segment before winter however, what we desperately need now is some form of Insulation Material for the Roof and Walls.

 

If you or your Company can help with Materials or Money then please contact Bob, or drop a message to the Secretary via the "Contact Us" page.

Home » Welcome » Our Facilities » The Barn Project » The Barn October 2014
100_6465web.jpg
100_6465web.jpg
100_6435web.jpg
100_6435web.jpg
100_6439web.jpg
100_6439web.jpg
100_6441web.jpg
100_6441web.jpg
100_6449web.jpg
100_6449web.jpg
100_6457web.jpg
100_6457web.jpg
100_6462web.jpg
100_6462web.jpg
100_6464web.jpg
100_6464web.jpg

Progress up to the Ploughing Weekend 15/16 September 2012

Home » Welcome » Our Facilities » The Barn Project » The Barn Phase 1
Clutter Relocation
Clutter Relocation
Ground Clearance
Ground Clearance
Ground Clearance
Ground Clearance
Ray the Ace Digger Driver takes 5
Ray the Ace Digger Driver takes 5
Clearing the Ground
Clearing the Ground
Almost level
Almost level
Dave cleaning up the metal to earth the welder
Dave cleaning up the metal to earth the welder
Charlotte is the Gaffer!
Charlotte is the Gaffer!
Jason Welding
Jason Welding
Jason Welding
Jason Welding
Jason Welding
Jason Welding
Sparks
Sparks
March & April 2012 sees the Barn Project starting in earnest with initial ground preparation/clearance followed by the first of the structural changes - Welders R Us.
Brackets
Brackets
Brackets
Brackets
The new roof will go there
The new roof will go there
Still a bit to do
Still a bit to do
Brackets in place
Brackets in place
New roof supports in place
New roof supports in place
Cross beams and the new roof supports being fitted
Cross beams and the new roof supports being fitted
Cross beams
Cross beams
More beams
More beams
All square in reality
All square in reality
Dave Piller driving
Dave Piller driving
Its starting to look different
Its starting to look different
May 2012 Hardcore laying
May 2012 Hardcore laying
May 2012 Ted & Robin and a few tons of Hardcore
May 2012 Ted & Robin and a few tons of Hardcore
Home » Welcome » Our Facilities » The Barn Project » The Barn May 2012
Are they beams or stringers?
Are they beams or stringers?
Looking very square
Looking very square
We will remove the old roof eventually
We will remove the old roof eventually
Watch this space!
Watch this space!
Still a bit to do here
Still a bit to do here
View back towards the Club House
View back towards the Club House
Ready for the arrival of our Container
Ready for the arrival of our Container
The Container will go here
The Container will go here
We have a Container and its in the right place
We have a Container and its in the right place
The Container will provide extra secure storage
The Container will provide extra secure storage
I wonder where its been
I wonder where its been
The Container - ready for business
The Container - ready for business
Roy up the ladder
Roy up the ladder
Old Tommy holds the ladder
Old Tommy holds the ladder
Roy showing the scale of the building
Roy showing the scale of the building
More beams
More beams
View towards the end where the Barn will be extended
View towards the end where the Barn will be extended
Ready for the next phase
Ready for the next phase
All square
All square
20th May 2012
20th May 2012
Progress up to the Jubilee Weekend 2/3 June 2012
Home » Welcome » Our Facilities » The Barn Project » The Barn June 2012
Cherry Picker1
Cherry Picker1
Cherry Picker2
Cherry Picker2
Cherry Picker3
Cherry Picker3
roof removal
roof removal
0
0
roof removal
roof removal
roof removal
roof removal
roof removal
roof removal
roof removal
roof removal
roof removal
roof removal
0
More plant arrives
More plant arrives
0
0
0
View from the field
View from the field
View from the field 2
View from the field 2
Roof removal
Roof removal
Roof removal
Roof removal
Roof removal
Roof removal
All this is coming down
All this is coming down
0
Steel sections awaiting the drop
Steel sections awaiting the drop
Removal of the old metal roof sheets
Removal of the old metal roof sheets
More sparks as the tin sheets are cut away
More sparks as the tin sheets are cut away
Shortening the Steel supports
Shortening the Steel supports
Shortening the Steel supports
Shortening the Steel supports
coming down
coming down
Shortening the Steel supports
Shortening the Steel supports
Shortening the Steel supports
Shortening the Steel supports
Partly cut steel
Partly cut steel
Partly cut steel
Partly cut steel
Shortening the Steel supports
Shortening the Steel supports
Shortening the Steel supports
Shortening the Steel supports
Removal of cross beam
Removal of cross beam
lowering cross beam
lowering cross beam
Shortening the Steel supports
Shortening the Steel supports
Shortening the Steel supports
Shortening the Steel supports
Progress with the roof in October 2012

Home » Welcome » Our Facilities » The Barn Project » The Barn September October 2012
Overall roof - not quite but getting there.
Overall roof - not quite but getting there.
Roof end
Roof end
Roof end
Roof end
The view from inside the field.
The view from inside the field.
Taken on the day of the Ploughing Competition.
Taken on the day of the Ploughing Competition.
Head in the Clouds
Head in the Clouds
Going Up or Coming Down?
Going Up or Coming Down?
Teamwork
Teamwork
Teamwork too
Teamwork too
Top Job
Top Job
Ill make the Tea
Ill make the Tea
Ladder Man
Ladder Man
Its supposed to look like this
Its supposed to look like this
Working on the second bay
Working on the second bay
GEDC0033weblo.jpg
GEDC0033weblo.jpg
Roofers R Us
Roofers R Us
Just a bit more to do
Just a bit more to do
Looking more complete
Looking more complete
Progress
Progress
Progress
Progress
Looking lengthwise
Looking lengthwise
Looking lengthwise
Looking lengthwise

2014 is here and much work has already been done. Here are a few shots taken in March and April 2014. The images do not do justice to what is becoming a very large and usable space.

Home » Welcome » Our Facilities » The Barn Project » Building the Barn in 2014
GEDC0235web.jpg
GEDC0235web.jpg
GEDC0205web.jpg
GEDC0205web.jpg
GEDC0206web.jpg
GEDC0206web.jpg
GEDC0207web.jpg
GEDC0207web.jpg
GEDC0208web.jpg
GEDC0208web.jpg
GEDC0209web.jpg
GEDC0209web.jpg
GEDC0210web.jpg
GEDC0210web.jpg
GEDC0211web.jpg
GEDC0211web.jpg
GEDC0217web.jpg
GEDC0217web.jpg
GEDC0218web.jpg
GEDC0218web.jpg
GEDC0219web.jpg
GEDC0219web.jpg
GEDC0220web.jpg
GEDC0220web.jpg
GEDC0223web.jpg
GEDC0223web.jpg
GEDC0224web.jpg
GEDC0224web.jpg
GEDC0225web.jpg
GEDC0225web.jpg
GEDC0226web.jpg
GEDC0226web.jpg
GEDC0227web.jpg
GEDC0227web.jpg
GEDC0231web.jpg
GEDC0231web.jpg
GEDC0233web.jpg
GEDC0233web.jpg

 July and August, no let up With thanks to Robin and John Wright for their generosity and with the help and support of the rest of the Concreting Team we were able to complete a significant milestone in the Barn rebuild on 17th May 2014. Have a look at the slideshow or video for a sample of how the day went.

GE DIGITAL CAMERAGE DIGITAL CAMERA

Download The Concrete Gang

here

Title

File Type

The Concrete Gang May 2014 (4459 downloads ) pdf document
The Concrete Gang May 2014 (4257 downloads ) Video

Home » Welcome » Our Facilities » The Barn Project » The Barn July/August 2014
GEDC005149.jpg
GEDC005149.jpg
GEDC001110.jpg
GEDC001110.jpg
GEDC001211.jpg
GEDC001211.jpg
GEDC001312.jpg
GEDC001312.jpg
GEDC001413.jpg
GEDC001413.jpg
GEDC001514.jpg
GEDC001514.jpg
GEDC001615.jpg
GEDC001615.jpg
GEDC002725.jpg
GEDC002725.jpg
GEDC003432.jpg
GEDC003432.jpg
GEDC003533.jpg
GEDC003533.jpg
GEDC003634.jpg
GEDC003634.jpg
GEDC003735.jpg
GEDC003735.jpg
GEDC004846.jpg
GEDC004846.jpg
GEDC004947.jpg
GEDC004947.jpg
GEDC005048.jpg
GEDC005048.jpg
GEDC0111108.jpg
GEDC0111108.jpg
GEDC007370.jpg
GEDC007370.jpg
GEDC007471.jpg
GEDC007471.jpg
GEDC007572.jpg
GEDC007572.jpg
GEDC007673.jpg
GEDC007673.jpg
GEDC007774.jpg
GEDC007774.jpg
GEDC009390.jpg
GEDC009390.jpg
GEDC009592.jpg
GEDC009592.jpg
GEDC009693.jpg
GEDC009693.jpg
GEDC010198.jpg
GEDC010198.jpg
GEDC010299.jpg
GEDC010299.jpg
GEDC0103100.jpg
GEDC0103100.jpg
GEDC0104101.jpg
GEDC0104101.jpg
GEDC0105102.jpg
GEDC0105102.jpg
GEDC0106103.jpg
GEDC0106103.jpg
GEDC0107104.jpg
GEDC0107104.jpg
GEDC0108105.jpg
GEDC0108105.jpg
GEDC0109106.jpg
GEDC0109106.jpg
GEDC0110107.jpg
GEDC0110107.jpg